Your PNM bill jumped. The state wants to know why.

A hot month is charged at PNM's highest prices, and this summer the company guessed what many customers used.

What the public records and data show, with the sources listed at the end. How we label stories The editor chose this story and directed the research and writing, using AI tools, and checked it before it went up. How we label stories
The top of the PNM Building in Albuquerque, a pale concrete tower with rows of recessed windows and the company's teal PNM sign against a blue sky
The PNM Building in downtown Albuquerque, photographed in 2022. Photo: Xnatedawgx (cropped) · CC BY-SA 4.0

The short version

  • PNM charges more for power in June, July and August, and in those months everything a home uses above 900 units costs the most of all.
  • It takes about 4,450 units of power in one month to run a summer bill past $1,000, eight times what an average home uses in a month.
  • The attorney general's office gave PNM until Sept. 23 to explain. Neither it nor utility regulators have announced an investigation.

A Deming woman’s July bill from PNM came to almost $1,100, and August was over $1,000 again. “Take ownership for what the problem is,” she told KOB.

She has plenty of company. The average PNM household is spending about 20% more on electricity than it did in 2019, and it is not because homes use more. Homes used a little less over those six years.

Since 2019: the bill is up, the power used is not
-5.2%8.8%22.9%2019 level2019202020212022202320242025What the average household pays a year, 2019: 0.0%What the average household pays a year, 2020: 11.8%What the average household pays a year, 2021: 11.2%What the average household pays a year, 2022: 10.4%What the average household pays a year, 2023: 16.4%What the average household pays a year, 2024: 18.4%What the average household pays a year, 2025: 20.2%0.0%20.2%How much power it uses, 2019: 0.0%How much power it uses, 2020: 5.5%How much power it uses, 2021: 1.6%How much power it uses, 2022: 1.7%How much power it uses, 2023: 1.5%How much power it uses, 2024: 0.8%How much power it uses, 2025: -2.5%-2.5%
  • What the average household pays a year
  • How much power it uses

In 2019 the average PNM household paid $907 a year for 6,839 units of power. Last year it paid $1,090 for 6,665 units. A Ledger calculation from the federal Energy Information Administration's Form EIA-861 detailed data files, pulled September 15, 2026, counting everything PNM billed, including the fuel charge and riders. The 2025 figures are an early release and may be revised.

Show the numbers
YearWhat the average household pays a yearHow much power it uses
20190.0%0.0%
202011.8%5.5%
202111.2%1.6%
202210.4%1.7%
202316.4%1.5%
202418.4%0.8%
202520.2%-2.5%

The increase everyone remembers, though, is not why summer bills came in so high.

A hot month is billed at PNM’s highest prices

Rates did go up on April 1. PNM had asked regulators for $174 million a year and settled for $105 million, in two steps. For a typical home, April’s step added about $6.23 a month. That is not what turns a normal bill into a shocking one.

Another piece of the bill moved the other way. The fuel charge covers what PNM pays for the fuel it burns and the power it buys, it is reset every three months, and it falls on part of a home’s power rather than all of it. Counted that way it has dropped by more than two fifths, from about 3.5 cents a unit last October to about 2 cents this July.

The damage comes from how PNM prices a summer month. The first slice of power a home uses each month is the cheapest it will buy, and everything after that costs more, most of all in June, July and August. For a home already past 900 units that month, every extra hour of air conditioning in August is bought from the dearest slice of all.

The top tier is where a big bill is made

What does it take to run a summer bill past $1,000? Worked back through PNM’s rate sheet, it takes about 4,450 units of power in a single month, eight times what an average PNM home uses and about two thirds of what it burns in a year.

Most of a bill that size is the power itself, and most of the power sits in the top tier. Everything above 900 units in a summer month is charged at PNM’s dearest rate, and on a $1,000 bill that slice alone comes to about $700.

Where a $1,000 bill comes from
An average month, 555 unitsAn average month, 555 units, The first 900 units: $56An average month, 555 units, Everything above 900: $0An average month, 555 units, Fuel, riders and the fixed charge: $34$90A hot month, 1,200 unitsA hot month, 1,200 units, The first 900 units: $107A hot month, 1,200 units, Everything above 900: $60A hot month, 1,200 units, Fuel, riders and the fixed charge: $61$228A $1,000 bill, 4,450 unitsA $1,000 bill, 4,450 units, The first 900 units: $107A $1,000 bill, 4,450 units, Everything above 900: $708$708A $1,000 bill, 4,450 units, Fuel, riders and the fixed charge: $184$184$1,000
  • The first 900 units
  • Everything above 900
  • Fuel, riders and the fixed charge

A Ledger calculation from PNM's residential rate sheet, its published fuel charge for July 2026 and its five rider filings, all pulled September 15, 2026. A unit is a kilowatt-hour. Summer rates apply in June, July and August. The first 900 units cost the same on any bill that goes past them; it is the slice above 900 that grows. Before the city franchise fee and the gross receipts tax, which vary by address. An average PNM household used 6,665 units in 2025, or 555 a month.

Show the numbers
The billThe first 900 unitsEverything above 900Fuel, riders and the fixed chargeTotal
An average month, 555 units$56$0$34$90
A hot month, 1,200 units$107$60$61$228
A $1,000 bill, 4,450 units$107$708$184$1,000

Then PNM ran short of meter readers

In mid-July PNM ran short of meter readers in southern New Mexico, and within weeks the shortage had spread north to Albuquerque. About one in five customers were affected, and may have seen a bill estimated or late, a PNM spokesman told KRQE in August.

An estimated bill is a guess, worked out from last month’s reading and whatever the house used a year ago. Guess low, and the shortfall shows up whenever somebody finally reads the meter, sometimes as more than one month of power on a single bill. In Alamogordo, residents said bills covering two months on one statement pushed their usage into the highest-priced rate tier.

The state wants answers

On Sept. 10 the attorney general’s office wrote to PNM, asking why so many bills were estimated, whether the company had filed its method for estimating with the state, and whether the shortage was foreseeable. The letter, from Mark Hayden, director of the office’s utilities unit, to TXNM Energy President and CEO Don Tarry, gave PNM until Sept. 23 to respond.

Neither the office nor utility regulators have announced an investigation.

PNM has apologized for the confusion the shortage caused and, advocacy staff at the Public Regulation Commission say, suspended late fees and disconnections for affected customers. October’s bills will come from a real reading, it told KOB.

Blackstone still wants to buy PNM

Waiting on the other side of all this is Blackstone, which agreed last year to buy PNM’s parent company in a deal valued at $11.5 billion including debt, and still needs the same regulators to approve it. On Sept. 15 the companies offered $220 million in bill credits over ten years, which PNM projects would take about 3.5% off a typical bill for the first four.

Nothing in the offer stops PNM from asking for higher rates. When the same regulators approved the sale of New Mexico Gas Co. this summer, they required a freeze on base rates through January 2028.

PNM’s answer is due Sept. 23.

Updated Oct. 14, 2026: We revised this story to source its facts to public records where we could, and removed details and quotes we could not confirm from a record.

Reader comments

What do you think?

Burqueños know this city best. Add what you've seen, ask a question, or push back on the story.

Loading comments…

Sign in to comment

New here? Sign up with your email. Confirm it and you're in, no password.

Comments are the commenter's own words, not the Ledger's. Comment rules

Where this came from

This story draws on the reporting and public records listed here. Where they differ from this page, go by the original.

  1. AG's office presses PNM on 'unusually high' customer bills New Mexico Department of Justice
  2. Shocked by 'extreme' PNM bills, Alamogordo residents demand answers New Mexico Political Report
  3. NMDOJ questions PNM about billing practices KOB
  4. PNM customers may see delayed or larger bill as company experiences shortages in meter readers KRQE
  5. Customer notice: PNM rate change effective April 1, 2026 New Mexico Public Regulation Commission
  6. Unopposed comprehensive stipulation in PNM's 2025 rate request, case 24-00089-UT PNM, filed with the New Mexico Public Regulation Commission
  7. Residential service, 26th revised Rate No. 1A PNM
  8. Residential service, 27th revised Rate No. 1A PNM
  9. Fuel and purchased power cost adjustment, effective July 1, 2026 PNM
  10. Fuel and purchased power cost adjustment clause, 11th revised Rider No. 23 PNM
  11. Fuel and purchased power cost adjustment reset, October through December 2025, case 22-00270-UT PNM, filed with the New Mexico Public Regulation Commission
  12. Transportation electrification rider, fourth revised Rider No. 53, Advice Notice 650 PNM
  13. Grid modernization rider, original Rider No. 60, corrected Advice Notice 653 PNM
  14. Energy transition charges, fifth revised Rider No. 51, Advice Notice 654 PNM
  15. Energy efficiency rider, 32nd revised Rider No. 16, Advice Notice 655 PNM
  16. Renewable energy rider, 29th revised Rider No. 36, Advice Notice 652 PNM
  17. PNM Franchise Ordinance, franchise fee, section 13-4-2-4 City of Albuquerque Code of Ordinances
  18. Annual Electric Power Industry Report, Form EIA-861 detailed data files U.S. Energy Information Administration
  19. Estimated bill PNM
  20. Press releases, September 2026 New Mexico Department of Justice
  21. Joint Applicants' motion to revise merger application, with revised regulatory commitments, case 25-00060-UT PNM, TXNM Energy and Troy ParentCo, filed with the New Mexico Public Regulation Commission
  22. Commission approves sale of New Mexico Gas Company New Mexico Public Regulation Commission
  23. TXNM Energy enters agreement to be acquired by Blackstone Infrastructure (Form 8-K, exhibit 99.1) TXNM Energy, U.S. Securities and Exchange Commission
Cite this story
APA

Duke City Ledger. (2026, September 16). Your PNM bill jumped. The state wants to know why. Duke City Ledger. https://dukecityledger.com/news/pnm-blackstone-attorney-general/

MLA

“Your PNM bill jumped. The state wants to know why.” Duke City Ledger, 16 Sept. 2026, https://dukecityledger.com/news/pnm-blackstone-attorney-general/.

Chicago

Duke City Ledger. “Your PNM bill jumped. The state wants to know why.” Duke City Ledger, September 16, 2026. https://dukecityledger.com/news/pnm-blackstone-attorney-general/.

Credit and republishing guidelines

Know something about this story? Send a tip.

More from the Ledger

All Business →